For more details about KSA's brand new building click here.
25.05.12
The finishing touches to the internal works are now going on. The sprung floor has been installed in the sports hall and drama studio and the raised seating and carpet have gone into the lecture theatre. Detailed work to the arts and science gardens has got under way, along with other planting around the outside of the building. The main entrance is also taking shape (pictured).
|
 |
21.04.12
The rainwater harvesting system is now complete, as is the electrical cabling. Some furniture is being installed. Perimeter footpaths have been laid.
|
 |
23.03.12
Ceilings to the library and restaurant are being installed. Door frames are being painted.
Street lighting has started along rear drive and the bank to the East elevation has been graded to its final position.
|
 |
10.02.12
Internal classroom windows have gone in and work has started to install the steel staircases in each faculty.
|
 |
06.01.12
The glazed walls to the study terrace are now complete, along with the theatre windows. The framework for the toilet partitions have started to go in.
|
 |
15.12.11
Brickwork is now complete and windows are now fitted in the different faculties. The under floor heating pipework is complete to the changing rooms.
|
 |
04.11.11
External brickwork was finished this month. Internal blockwork to the restaurant is now complete. Work has started to the main entrance roof. Drainage is 75% complete.
|
 |
14.10.11
Windows have been fitted to the MIT and Comms faculties and underfloor heating pipework is ongoing.
Brickwork is 99% complete on the ground floor and the full height glazed windows are going up on the study terrace.
|
 |
30.09.11
The new building is really taking shape now. Brickwork on the ground floor is 97% complete.
The roof to the theatre and sports hall is now complete.
Drainage is 75% complete and internal blockwork to the library has started.
|
 |
26.08.11
Brickwork to the theatre is almost complete.
|
 |
29.07.11
Brickwork to the theatre (pictured) continues.
|
 |
15.07.11
Phase 1 brickwork and blockwork is ongoing and the energy centre brickwork is complete.
The ground floor slab concrete pour in science is complete.
The transformer has been delivered and installed.
|
 |
17.06.11
Mechanical and electrical works have started and the application of fire-paint protection to steelwork is ongoing.
Brickwork in the MIT and Comms faculties on-going.
|
 |
20.05.11
The blockwork and brickwork is now under way and will be on-going for about 4 to 5 months.
The installation of roof sections and membranes for the sports hall and theatre also got under way this month.
|
 |
01.04.11
The steelwork is now complete for phase 3, which includes the science department, sports hall and Comms department.
Floor planks are being installed in the Maths and IT block.
Steel work for the community access bridge is due to go up soon.
|
 |
18.02.11
The steelwork for the entrance bridge (which will be the main entrance point to KSA) is now complete. Part of this can be seen to the very left of the photo.
Structural work to the main courtyard area continues.
Next to go up will be the steelwork for phase 2, which includes the Maths and IT faculty.
|
 |
08.02.11
Much of the steelwork in phase 1 is now complete, including the Art, Music and Industrial Design Faculty, the theatre, dance and fitness studios, lecture theatre and drama studio.
|
 |
24.01.11
There is excitement as the new building starts to take shape at a rapid pace and it is closely watched by students and staff.
The steelwork for phase 1 is ongoing, with the structural work for the fitness and dance studios and changing rooms now complete.
Upgrade works to pitches is now complete.
|
 |
19.01.11
Groundworks continue, including work for the ground-source heating system which will make the Academy one of the greenest buildings in the county.
A ground-breaking ceremony with all those who have been involved with the new build will be held on the 19th.
|
 |
|
12.11.10
The top soil is stripped in the building area and lower pitch and drainage material arrives on site - the next stage will be setting up connections to the main drain.
Offices and access points have been established for construction staff.
|
 |
|
20.10.10
After months of planning KSA's new build, things start happening on site with the first delivery of materials.
Preparations for the groundworks get under way and there is more activity each day.
|
 |
|
|